Sheraton Tysons West Hotel

sheraton tysons.jpg

Vienna, VA
50,000 SF; $1.5 Million
Owner: JBG Smith
Client: JBG Smith
Role: Project Management

The project includes phased selective demolition and repair of an elevated parking structure.  Existing finishes at the upper level parking deck will be selectively removed to allow structural repairs to the steel and concrete composite structure.  Following repairs, finishes and landscaping will be restored. Critical project elements include design management, safety and logistics, budget and cost control, careful phasing and coordination with the on-going operations of the hotel and landscaping restoration at the upper parking deck islands and planters. Hanscomb is providing full project management services, including design phase and construction phase management oversight.